6.5.2 ISSUE AND RECEIPT {Page 1}
- An Issuer shall confirm the authorisation level of the Acceptor.
- When Drain Earths are required the number of Drain Earths issued shall be recorded on the Safety Document and an associated Earthing Schedule issued.
- The Issuer shall sign the issue part of the Safety Document and shall issue it together with one of the key(s) that maintain Joint Control of the isolation. He shall also issue those items listed on the Safety Document.
- Where a Permit (ROSH), Permit (TEST) or Permit (LIVE) is issued, an Approved procedure shall be issued to the Acceptor of the Permit (ROSH), Permit (TEST) or Permit (LIVE), along with any Safety Keys necessary to meet the terms and conditions of the Permit (ROSH) or Permit (TEST).